State Highway 69 Reconstruction
Construction is scheduled to take place summer of 2019. During construction, the roadway will be closed to through traffic. Access to residences and bisinesses throughout the corridor will be maintained.
The project begins near the intersection of County Road D in Belleville, WI and extends north approximately 8.56 miles to the intersection of Valley Road.
Project update/next steps-Project schedule
Public Information Meeting #1 April 13, 2015
Public Information Meeting #2 April 14, 2015
30% Plans April 2015
Environmental Document November 2015
60% Preliminary Plans January 2016
Public Information Meeting #3 March 2016
90% Draft PS&E August 2017
FInal PS&E May 2018
Construction Summer 2019